shaft.
Install the rest of the rack assemblies and then install the cross-
overs. Each rack and crossover is numbered or identified as to its position.
Figure 2-11 shows the correct positioning.
5. You are now ready to install the roll-feed adapter (or magazine assembly)
and roll film take-up assembly if they are required.
6. The processor should be filled with chemicals using the required developer
and fixer.
It must be filled to the proper level using an external source.
The replenisher system is not designed for initial filling of the chemical
tanks. Once the tanks are filled, check the replenisher system for operation.
To do so, proceed as follows:
a. Make sure the lines are connected to the inputs and the storage tanks
are filled with solutions.
b. Turn the replenisher switch to the MANUAL position.
c. Open the bleed valve inside the plumbing chamber to remove the air from
the lines. When the solution flows, close the valve.
d. Open flow meter control valves and allow the solutions to flow through
the flow meters to the tanks.
e. Adjust the flow meters to the desired replenishment rate.
f. Turn the replenisher switch to the OFF position.
7. Replace the side panel for the plumbing compartment and allow 5 to 10
minutes for the developer and dryer assembly to come up to the required
temperature. Turn on the cold and hot water and adjust the mixing valve to the
recommended water temperature (slightly less than the recommended developer
temperature).
The water temperature is indicated by a thermometer on the
mixing valve.
Before the initial processing operation, check the developer
temperature with a process thermometer to ensure the machine thermometer is
correct.
After the initial check and correction, this check is performed
periodically during the maintenance inspections.
16