LESSON 1
ORGANIZATIONAL PLANNING
CREDIT HOURS ......................... 2
TEXT ASSIGNMENT ...................... Addendum A, para 1-1 thru 6-3
MATERIALS REQUIRED ................... None
LESSON OBJECTIVE ..................... To familiarize you with outside plant
construction project planing, route
surveying, work time and sequence
planning, project safety precautions,
use
of
signals
in
directing
operations, and the maintenance of
construction records.
SUGGESTIONS .......................... None
EXERCISES
In each of the following exercises, select the ONE answer that BEST
completes the statement or answers the question. Indicate your solution by
circling the letter opposite the correct answer in the subcourse booklet.
1.
Information concerning circuit requirements, service area
size and
location, and provisions for expansion are included in the
a.
route survey map.
c.
advance plan.
b.
layout crew map.
d.
signal plan.
2.
The survey party selects the most practical route for the line
construction project and marks it for the layout crew. In addition,
the survey party
a.
stakes out the pole line.
b.
prepares a material estimate.
c.
arranges for right-of-way clearances.
d.
includes a pilot for the layout crew, if needed.
1