9.
Using table 3-I, how many manhours will it take a construction crew to
bury 3 miles of spiral-4, two cables in the same trench? A cable plow
will be available and this operation will take place in a jungle area.
a.
25.5 manhours
c.
135.0 manhours
b.
36.0 manhours
d.
Figure unknown
10.
Construction crews are briefed before being dispatched to the project.
To insure that details are correct, the briefer may use the
a.
route map.
c.
detailed plan.
b.
advance plan.
d.
construction plan.
11.
TM 11-2262-1, table 3-II, contains a list of the common tools and
equipment used by construction crews. What equipment is used to lift
and support cable reels?
a.
Bar LC-3
c.
Roller LC-26
b.
Jack LC-13
d.
Hook LC-48
12.
Accidents do not just happen, they are caused.
On construction
projects, observation of safety regulations is the responsibility of
a.
the signal officer.
c.
the project engineer.
b.
the crew supervisor.
d.
all personnel concerned.
13.
Extreme caution is recommended when working in the vicinity of power
lines and equipment. When hazardous conditions cannot be eliminated,
operations are conducted under the direct supervision of the
a.
crew chief.
c.
safety supervisor.
b.
signal officer.
d.
project engineer.