5.
In an emergency situation, how many steps are taken to stop the
generator?
a.
3.
b.
1.
c.
5.
d.
4.
6.
The initials MEP stand for _______________.
a.
Mobile electric power.
b.
Mobile engineer power.
c.
Metric engineer power.
d.
None of the above.
7.
The ground rod (with attachments) is a component of PU-617/G.
a.
True.
b.
False.
8.
Why is generator set PU-628/G categorized as a special purpose
generator set?
a.
It transports and stores cable reels.
b.
It contains fuel tanks.
c.
All of the above.
d.
None of the above.
9.
When selecting a site for installation of generator sets
PU-617/M, PU-625/G or PU-628/G, you must avoid muddy, sandy, and
dusty location if possible.
a.
True.
b.
False.
30