INTRODUCTION (con't)
STANDARDS:
Correctly install a telephone substation within 2 hours.
TASK:
Troubleshoot a defective telephone substation/line
CONDITIONS:
Given a preinstalled defective substation/line, linemans pliers, terminal wrench,
diagonal pliers, long nosed pliers, telephone test set, small and large flat tip
screwdriver, electrical or friction tape, safety hat, TE-21 kit, DA Form 4174
(telephone trouble report), FM 11-372-8.
STANDARD:
Correctly troubleshoot a telephone substation/line by locating and recording faults
found on DA Form 4174 within 45 minutes.
Performance-Oriented (Multiple-choice) terminal learning objectives:
TASKS:
Install telephone substation and troubleshoot a defective telephone substation/line.
CONDITIONS:
Given Lessons 1, 2, and 3 materials, pencil, paper, and without supervision.
STANDARDS:
Demonstrate competency of the tasks skills and knowledge by correctly
responding to 70 percent of the multiple-choice test covering installation of
telephone substation and troubleshooting a defective substation/line.
x